Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

The planned duration will be determined as amount of working days between planned start date and planned end date taking the assignee's calender into account as well as weekends, company holidays etc. The baseline duration will be calculated accordingly using baseline start date and baseline end date. The acutal duration will be calculated as sum of estimated remaining effort and the amount of working days between actual start date and actual end date. If an issue has not been finished, the actual end date has not been set and is unavailable. In that case, the current date (today) will be used instead.

Info
titleSystem Admin TODO
To set the content of custom field "actual end" to current date, it is necessary to configure your JIRA's workflow to send an event "ISSUE_RESOLVED".

Schedule Variance based on actual planning (SVa)

...