Gantt-Chart offers you additional information for steering your tasks based on earned value analysis since Gantt-Chart version 3.2.

Table of Contents

Please open the Gantt menu (cog icon) on the right top, choose menu item "configure columns & rows" and switch to tab "columns". Select the preferred column you want to add and click on button "add". The new column will be appended within the preview. If the preview exceeds your screen width, you can scroll left/right. Clicking on arrow icons per column name, you can re-order the columns or remove them via click on the trash icon.

...

The planned duration will be determined as amount of working days between planned start date and planned end date taking the assignee's calender into account as well as weekends, company holidays etc. The baseline duration will be calculated accordingly using baseline start date and baseline end date. The acutal duration will be calculated as sum of estimated remaining effort and the amount of working days between actual start date and actual end date. If an issue has not been finished, the actual end date has not been set and is unavailable. In that case, the current date (today) will be used instead.

Info
titleSystem Admin TODO
To set the content of custom field "actual end" to current date, it is necessary to configure your JIRA's workflow to send an event "ISSUE_RESOLVED".

Schedule Variance based on actual planning (SVa)

SVa = (actual duration - planned duration) / planned duration * 100

Schedule Variance based on

...

baseline (SVb)

SVb = (actual duration - baseline duration) / baseline duration * 100

...